Project: TG Eakin - New Warehouse Build

Client: Henry Brothers

Duration: 13 months

The works included on this job were the excavation of approx. 14,000m3 across the site and removal off-site, all foundation works including the setting of the bolt boxes and formation of ground beams. We installed the complete storm and foul drainage throughout the site and all associated ducting works. All kerbing works to the perimeter of the building and car park were also under our scope of works.