Project: A6 Dualling Dungiven to Drumahoe
Client: Sacyrs Wills Somague JV
Duration: 3 months
As part of the initial enabling works we were tasked with a service diversion of an existent overhead NIE Line. This consisted off approx. 700m of trenching across the site, with attendance to NIE in laying and backfilling of the cable.
Following on from that we installed approx. 500m of a concrete Accommodation laneway to allow earthworks to start. This consisted of a cut and fill of approx. 2500m3, 500m of filter drainage, water main and service ducting. The verges of the laneway were then top soiled and left ready for grass seed.